Westport Flood Protection Scheme

Reset

Kawatiri Coastal Trail - Carter's Beach Westport

Community information evenings

We held community information evenings on 22 and 24 Septembr 2026 in Westport.

They cover off a lot of information about what the consultation is about and the project reset process to arrive at the counsultation options. If you couldn’t make the meeting or would like to go over the content again, you can read or download the full presentation here.

A recording of the meeting held on 22 September 2026 is also available on the WCRC YouTube page.

In 2026, a review of the Westport Flood Protection Scheme (WFPS) has been carried out, after it became clear that there were affordability issues.

The costs of the original scheme are now predicted to reach about $70 million, so the project team has worked on ways to reduce that and still deliver a more credible scheme.

One tool for doing so is to lower the level of protection to Westport to protect against an approximately 1 in 67-year flood (similar to July 2021) – as opposed to the 1 in 100-year previously proposed. The level of freeboard (extra height allowance for uncertainty) would also be reduced from 600mm to 400mm following enhanced computer modelling.

The project reset has financial implications for ratepayers and represents additional debt for West Coast Regional Council (WCRC).

These proposed changes represent a significant variation from what is included in the West Coast Regional Council’s current Long-Term Plan (2024-2034) and what was consulted on with the community in 2021. Therefore, additional consultation is required using a Special Consultative Procedure.‍ ‍

Special Consultative Procedure

A Special Consultative Procedure on the changes proposed to the Westport Flood Protection Scheme (WFPS) runs from Monday 21 September until 21 October 2026 at 5pm

The Special Consultative Procedure will ask the community to consider two options (below). Another option was considered but deemed too costly.

Option One is the main Westport Flood Protection Scheme (the Core Protection Scheme) built to a 1.5% AEP (Annual Exceedance Probability) protection level, based on the current climate, with 400mm of freeboard (extra contingency height). Plus, the revised alignment of the Carters Beach stopbank built to a 1.5% AEP, and 300mm of freeboard. This level of protection would protect Westport from a comparable flood to the July 2021 event but does not allow for future climate change.

Option Two is an Optimised Hybrid Scheme that builds on Option One for Westport and Carters Beach. It is designed for current climate conditions, with allowance to raise the height of the floodbanks in the future. The additional cost is estimated at about $1 million. The difference is that at select constrained locations, short sections of stopbank would be constructed with a wider footprint that can be cost-effectively built on in the future. For now, they would be built to the same height as Option One and offer the same level of flood protection.

Background:

On 25 August 2026, Regional Councillors approved Council undertaking a Special Consultative Procedure (SCP) on proposed scheme changes and voted to approve the next set of actions to progress the reset of the scheme.

At its 15 September 2026 extraordinary meeting, Regional Council approved the SCP going ahead, subject to auditor’s approval, which was granted on 18 September 2026.

The Special Consultative Procedure on the changes proposed to the Westport Flood Protection Scheme (WFPS) runs from Monday 21 September until 21 October 2026 at 5pm.

You can find out more and provide an online submission on the West Coast Regional Council website:  www.wcrc.govt.nz/community/consultation

The consultation is open to all, targeting those who live in and around the Westport Rating District (map shown). This includes Westport, Carters Beach and Snodgrass Road.

Cost implications

The tables below indicate the costings and rating implications of the proposed options:

Option One

Option Two

Special Consultative Procedure Process

25 August 2026 Extraordinary meeting to approve next steps for Project reset

15 September 2026 Extraordinary meeting to approve SCP

21 September 2026 Special Consultative Procedure scheduled to commence

21 October 2026 Consultation closes 5PM

27 October 2026 Hearings for SCP submissions to be held in Westport

December 2026 WCRC Meeting

To find out more:

You can attend one of our community drop-in sessions on Wednesdays between 11am and 1pm at 147 Palmerston Street, Westport.  

You can find out more and provide an online submission on the West Coast Regional Council website:  www.wcrc.govt.nz/community/consultation

What is the process once the Special Consultative Procedure is complete?

The results of the consultation will be analysed in October and collated into a report for the West Coast Regional Council. 

Public hearings for those who wish to speak to their submissions will be held on 27 October 2026 (11am-3pm approx). They will be held in Westport. 

The results of the Special Consultative Procedure will be placed before the full West Coast Regional Council in December 2026.

Your Questions Answered